2022 Alley Reconstruction

Print
Press Enter to show all options, press Tab go to next option

The master plan calls for the construction/reconstruction of nine (9) alleys in 2022. One (1) alley is gravel/grass and in poor condition, five (5) alleys are bituminous and in poor condition, and three (3) alleys are concrete and in poor condition. Without improvements of these alleys, these alleys will continue to warrant high maintenance costs along with further deteriorations until failure. The alleys proposed for improvement are listed below:

ALLEY FROM TO BETWEEN  
24-104 Carney Ave.Tile St.West 10th St.And West 11th St.
13-404 Willard St.West End West Pleasant St.And Fulton St.
13-437 Lewis St.North End Record St.And Byron St.
13-437 Record St.Byron St.Fulton St.And Lewis St.
13-477 Marshall St.Record St.Shaubut St.And Lewis St.
18-303 Byron St.Center St.Bradely St.And East Pleasant St.
18-304 Center St.Locke St.Bradely St.And East Pleasant St.
18-305 East Pleasant St.South End Locke St.And Prospect Ave.
18-328 Alley 18-305 East End East Pleasant St.And Terminous

Suggested improvements include reclaiming, reconstruction of bituminous or concrete surface, and installing of new storm sewer system where needed.

Latest project update

Friday, September 9, 2022

Alley 13-437 - Trees have been cleared and grubbed. XCEL Energy is scheduled to move utility poles.

Alley 18-303 - Subgrade excavation work is taking place. Subcontractor for Consolidated Communications is re-establishing cut cables.

Alley 18-304 - Aggregate base has been installed.

More updates

Project documents

No documents at this time.

rss

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player QuickTime Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer