Suggested improvements include pavement cracking/seating, bituminous surfacing, concrete surfacing, select curb and gutter, sidewalks and ADA accessibility improvements.
Project updates
Friday, September 11, 2026
Remaining punch list items got completed this week.
Friday, September 4, 2026
Punch list work on the Adams Street Resurfacing project between Raintree Road and State Highway 22 was completed this week.
Thursday, August 27, 2026
No activity on site this week.
Thursday, August 27, 2026
No activity on site this week.
Thursday, August 13, 2026
No activity on site this week.
Friday, August 7, 2026
No activity on site this week.
Friday, July 31, 2026
No activity on site this week.
Friday, July 24, 2026
No activity on site this week.
Friday, July 17, 2026
No activity on site the week of 7/13/26.
Friday, July 10, 2026
Final punch list work is currently being conducted.
Friday, October 3, 2025
Phase 1, which consisted of resurfacing Adams St. from Highway 22 to Raintree Rd., has been completed and Adams St. has been reopened. Phase 2 is expected to start Monday, Oct. 6 and last for approximately 2 weeks. Phase 2 consists of closing the intersection of Adams St. and Raintree Rd. for paving work.