Thursday, October 29, 2026
The ribbon cutting was held 10-27. Upcoming is enjoy the new bike trail!Thursday, October 22, 2026
The painting crew was on site finishing painting the piers. The railings across the span are complete.Friday, October 16, 2026
Final lift of bituminous pavement has been placed on both sides of river. Flower bed has been installed adjacent to Sibley Parkway. 70% of the railing has been installed. Road signage has been installed.
Upcoming work includes finish painting the piers. Finish installing the railing. Crosswalk painting.
Ribbon cutting celebrating the completion of the project is scheduled for Tuesday, October 27th at 1:00 pm on the Sibley Park side of the bridge.
Thursday, October 8, 2026
Ongoing work on the railing installation. The base course of pavement has been placed on Sibley Parkway and the service road on the Land of Memories side. Trail connections have been paved on both sides of the river. Black dirt has been placed on the Sibley Park side.
Upcoming work will include turf restoration, conclusion of the railing system, and the final lift of bituminous.
Thursday, October 1, 2026
Railings were installed on the approaches to the bridge on both sides of the river. Fine grading of Sibley Parkway and adjacent trails is occurring. Curb, apron and pedestrian ramps were installed at the bottom of the hill of CHS Pergola Way.
Upcoming work will be pavement on Sibley Parkway and adjacent trails, and the same on the Land of Memories side.
Wednesday, September 23, 2026
The wood curb was installed on the bridge span. They are forming curb and gutter and apron at the bottom of CHS Pergola Way. They are grading road for curb and gutter installation on LOM side.
Upcoming will be bituminous paving of the road and trail connections on the Sibley Park side. Installation of the guard railings.
Wednesday, September 16, 2026
The timber planks have been installed on the bridge deck. Concrete sidewalk has been installed on bridge approaches on both sides of the river. Street lights have been installed at Sibley Parkway. Curb and gutter has been placed on the road adjacent to bridge on the Land of Memories side. Trail connections have been prepped for pavement on the (LOM) side.
Upcoming work includes wood curb installation on the river span section of the bridge. Railing installation. Paving of the trail connections on the Land of Memories side and the road section in that area.
Thursday, September 10, 2026
Sidewalk approach has been poured on west side of Sibley Parkway. Electric hand holes have set at Sibley Parkway area. Sidewalk on abutment at Land of Memories Trail connection has been poured. Gravel base has been installed for roadway on (LOM) side of the river. Timber deck installation on the historic bridge section is ongoing.
Upcoming work includes curb and gutter installation for roadway on Land of Memories side. Paving of connecting trails in that same area.