Land of Memories Trail

Print
Press Enter to show all options, press Tab go to next option
Construct a paved trail along a former roadbed that has been revegetated. Construction of a retaining wall and the installation of lighting along the trail. 

Latest project update

Thursday, September 10, 2026
The retaining wall is complete.  The contractor will be on site to install the aggregate for the trail section and work on site restoration late the week of 9/7 into the week of 9/14.  The trail will sit unpaved over the winter to ensure we don't have settlement issues once the trail is completed.  The concrete trail section will be completed in the spring of 2027.
More updates

Project documents

No documents at this time.