Construct a paved trail along a former roadbed that has been revegetated. Construction of a retaining wall and the installation of lighting along the trail.
Project updates
Thursday, November 19, 2026
Work will resume in the spring of 2027. Friday, November 13, 2026
City staff placed planters at the entrance to Kern Bridge on both sides and the entrance to the trail at Amos Owen Lane to prevent vehicles from entering the trail and bridge.
Project will resume in the spring of 2027.
Friday, November 13, 2026
The final portion of the trail to complete at the retaining wall will resume in the spring of 2027. Friday, October 30, 2026
With Kern Bridge opening this week, we have pulled the barricade at the trail intersection with Amos Owen Lane. We will be installing some temporary bollards in the center of the trail entrances while we wait for the permanent bollards to arrive. The retaining wall section will be completed in the spring of 2027. Thursday, October 22, 2026
Work scheduled for this year on the trail is complete. Work with resume in the spring of 2027. Thursday, October 15, 2026
Work will resume in the spring of 2027. Thursday, October 8, 2026
No work until spring of 2027 Thursday, October 1, 2026
No work. Construction will resume in the spring of 2027. Thursday, September 24, 2026
Turf restoration work is complete and the safety fence is installed around the retaining wall. The 2026 portion of the work on the retaining wall is complete. It will sit over winter before installing the concrete trail and fence along the retaining wall. Allowing the area to go through a freeze and thaw cycle will help prevent settlement issues with the concrete. The trail will be paved in the spring of 2027. Thursday, September 17, 2026
Restoration work was completed around the retaining wall area. The project site will sit idle until the spring of 2027 when the concrete trail will be placed along the retaining wall. Thursday, September 10, 2026
The retaining wall is complete. The contractor will be on site to install the aggregate for the trail section and work on site restoration late the week of 9/7 into the week of 9/14. The trail will sit unpaved over the winter to ensure we don't have settlement issues once the trail is completed. The concrete trail section will be completed in the spring of 2027. Thursday, September 3, 2026
The retaining wall portion of the project was completed this week. The contractor has some grading work to complete and turf establishment before the project wraps up for the season. The contractor will place the aggregate base for the trail the week of 9/7. The plan is to let the trail sit unpaved through the fall and winter to allow it to go through a freeze and thaw cycle prior to the concrete paving being place. This allows the fill material time to settle preventing future issues with the concrete pavement. There will be a temporary safety fence installed along the retaining wall until the permanent fence can be installed after concrete is placed next spring. Thursday, August 27, 2026
Retaining wall work is ongoing. The contractor is continuing to set block and backfill and the go. They have five courses of block set with three courses remaining. The retaining wall work is expected to be complete the week of 8/31. Thursday, August 27, 2026
Work on the retaining wall is ongoing with really good progress made this week. The contractor has three courses of block set and is currently working on backfilling the third course. Work will continue for the next few weeks until the wall is completed. Thursday, August 13, 2026
Work on the retaining wall is ongoing. Crews were on site this week working on backfilling to first row of block. They started setting the second row late in the week. They will continue to set block and backfill for the next few weeks. Friday, August 7, 2026
The retaining wall portion of the project is expected to resume sometime during the week of 7/27. Thursday, August 6, 2026
Retaining wall work is underway. The contractor started working on excavation for the new backfill material and removed silted material from the base of the retaining wall to allow for the install of the drain tile and proper backfill material. They also began setting and backfilling the retaining wall block. Setting block and backfilling will continue for the next few weeks. Thursday, July 30, 2026
Construction of the retaining wall started this week with clearing of the site and prep work. The contractor will begin stacking the retaining wall block and installing the lightweight backfill material Monday, August 3rd. The project is projected to take five weeks depending on weather. Friday, July 17, 2026
The project is expected to resume the week of July 20th. Friday, July 10, 2026
Trail and retaining wall work adjacent to US Highway 169 is scheduled to resume the week of 7/13. The project has been on hold due to some unforeseen site conditions.