3rd Avenue (CSAH 5)

Print
Press Enter to show all options, press Tab go to next option
Complete reconstruction of all pavements, sanitary sewer (except the area beneath the railroad tracks), watermain, storm sewer, services to each lot, concrete curb and gutter, driveway aprons, sidewalks, street lighting, signage and pavement striping. 

Latest project update

Wednesday, September 16, 2026

     The gas company is working in the 1900 block.  Gravel base is being placed in the south half of the 1700 block.  Sidewalk work is ongoing in the 1300-1500 blocks.  The second lift of bituminous pavement has been installed on 3rd Ave. from Riverfront Dr. to just north of Spruce St.

     The detour for the neighborhood will be at Spruce St. beginning 9-17.  Chestnut and Pine Streets at 3rd Ave. will be closed for three weeks.

     Upcoming work will be curb and gutter, sidewalk connection, and retaining wall installation in the 1500-1600 blocks. 

More updates

Project documents

No documents at this time.

rss

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player QuickTime Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer