3rd Avenue (CSAH 5) Project updates

Print
Press Enter to show all options, press Tab go to next option
Complete reconstruction of all pavements, sanitary sewer (except the area beneath the railroad tracks), watermain, storm sewer, services to each lot, concrete curb and gutter, driveway aprons, sidewalks, street lighting, signage and pavement striping. 

Project updates

Wednesday, November 18, 2026

     The walls are complete with caps plus the main walk in front of them with the steps poured in the 1600 block.  Striping is complete from Riverfront to Brooks.  Temporary curb and catch basins are complete in the 1700 block.  Black dirt and erosion control blankets have been installed in 1200-1700 blocks.  The gas company is working on services and connections in the 1800-2200 blocks.

     Upcoming work includes safety railings on the block walls.  Outstanding flatwork in areas.  Ongoing gas service work.

Tuesday, November 10, 2026

     The walls are complete in the 1600 block backfilling operations are in progress.  They are prepping the boulevards for black dirt in the 1500-1700 blocks.  Sidewalk is 95% complete for this years portion of the 2 year project.  They are prepping the roadway north and south of the RR tracks for temporary pavement over the winter.  The gas company has ongoing connection work in the 2200 block and the Pine Street intersection.

     Upcoming work includes temporary railing installation on block walls in the 1600 block.  Turf stabilization.  Temporary pavement for the winter.  Gas company service work.

Tuesday, November 3, 2026

     Gas company is working on connections in the 1800 and the 2100 blocks.  Sidewalks are 90% complete in this years phase.  The modular block walls are 60% complete in the 1600 block.  This weeks rain events have halted progress thus far.  The 10 day forecast is looking good for upcoming operations.

     Upcoming work will include soil stabilization throughout project.  Gas service work.  Finishing the block walls in the 1600 block.  Sidewalk main line as the walls get completed. 

Thursday, October 29, 2026

     The gas company is working in the 1800 block.  The wall contractor is working on the retaining walls in the 1600 block.  Mainline sidewalk has been poured in the 1500 and the 1600 blocks.  The detour has been put back to Chestnut Street.  

     Upcoming work will include the forming and pouring of sidewalk connections at the intersections of Chestnut, Spruce and Pine Streets.  Ongoing wall construction in the 1600 block and wherever else they are required.  Restoration of roadway north of the RR tracks as the gas company finishes their main installation.  Black dirt installation as the sidewalk work is being completed.

Thursday, October 22, 2026

     The box culvert is in place and covered.  Crews are working on the forms for the concrete collar connecting the the new box to existing.  2 lifts of bituminous pavement have been placed from Spruce Street to south of RR tracks.  Gas company is working in Pine Street with flag people present.  Crews are raising castings on newly paved 3rd Avenue to street level.  Modular block is being delivered to site with the crew on site for wall construction.

     Upcoming work will include topsoil stabilization.  Sidewalk installation where ever needed.  Concrete collar pour for box culvert.

Wednesday, October 14, 2026

The box culvert has been installed with the catch basins on top of it and is being back filled in the 1800 block. They are forming the construction joint for the box culvert. The gas company is making the connection to their boring under the tracks in the 1700 block. Topsoil has been placed in the 1200 to 1400 blocks. Gravel base has been fine graded from Spruce Street to Pine Street along with Pine Street in preparation for paving.

Upcoming work includes bituminous pavement in the 1500-1700 blocks along with Pine St. starting 10-16. Topsoil stabilization in the 1200-1400 blocks. Sidewalk installation in the 1500-1600 blocks. Building the modular block walls in the 1600 block. Gas main connection on the north side of the RR tracks.

Thursday, October 8, 2026

     Black dirt work is happening in the 1200 to 1400 blocks.  Curb and gutter placement in the Pine St. intersection.  The gas company has bored and installed gas main under the RR tracks.  Contractor has dug out and placed rock foundation for the box culvert in the 1800 block.  Ongoing utility pole work in the 1800-2100 blocks.  Fiber cable work is ongoing in the 1500-1700 blocks.  Sidewalk and driveway work is ongoing in the 1500-1700 blocks.

     Upcoming work includes the placement of the box culvert.  Modular block wall placement in the 1600 block.  Turf establishment work in the 1200-1400 blocks.  Ongoing sidewalk and driveway work in the 1500-1700 blocks.

Thursday, October 1, 2026

Utility pole work is ongoing throughout project. Raising manholes and water valves to road surface for the winter from Riverfront to Spruce. Gas company has set up boring machine on the south side of the RR tracks to bore under the tracks to make the connection to the new gas main. Gas company is also working in the 2000 block.  

Upcoming work will be removal of the old culvert north of the tracks and install the new box culvert. Modular block walls in the 1600 block. Sidewalk installation in the 1300-1500 blocks. Black dirt and turf restoration in the 1200-1500 blocks.

Wednesday, September 23, 2026

     Utility pole work is ongoing in the 1200-1300 blocks.  Sidewalk has been graded out in the 1300-1500 blocks.  They are digging out for the modular block wall on the east side of the 1600 block.  They are also working on the box culvert in the 1800 block.  The gas company is working in the 2100 block.  The detour remains to be at Spruce St.

     Upcoming work will be pouring side walk in 1300-1500 blocks.  Radius curb and gutter work in the Chestnut intersection.  Box culvert installation, and modular block wall construction.

Wednesday, September 16, 2026

     The gas company is working in the 1900 block.  Gravel base is being placed in the south half of the 1700 block.  Sidewalk work is ongoing in the 1300-1500 blocks.  The second lift of bituminous pavement has been installed on 3rd Ave. from Riverfront Dr. to just north of Spruce St.

     The detour for the neighborhood will be at Spruce St. beginning 9-17.  Chestnut and Pine Streets at 3rd Ave. will be closed for three weeks.

     Upcoming work will be curb and gutter, sidewalk connection, and retaining wall installation in the 1500-1600 blocks. 

Thursday, September 10, 2026

The gas company is working in the 1900 block.  Utility pole work is ongoing in the 1500 block.  Testing and fine grading are ongoing in the 1200-1400 blocks.  Gravel road base has been installed in the 1600 block.  Excavation for the modular block walls has occurred in the 1600 block as well.  A lane closure has been set up on south bound Riverfront Drive for curb and sidewalk connection work going on on in that area.

The Chestnut cross over detour is being maintained during the ongoing work.  Upcoming work will be the base course of bituminous for the 1200-1400 blocks, just north of Spruce Street.  Sidewalk will be ongoing in the 1300-1400 blocks along with modular block wall construction in the 1600 block.  Box culvert installation north of the railroad tracks will be installed as well.

Wednesday, September 2, 2026

     Gas company is working in the 1800 & 1900 blocks with flaggers present.  Curb and gutter has been installed completely from Riverfront to Spruce St.  All sanitary, storm, and watermain has been installed from 1200 to 1700 blocks.  All sewer and water services have been connected and the temporary water system has been removed.  The RXR crossing has been completed.  Excavation for modular block wall is ongoing in the 1600 block.  

     Chestnut St. continues to be the main detour crossing into the neighborhood area.  Upcoming work will be curb and gutter mainline installation in the 1500 block.   Modular block wall construction in the 1600 block.  Box culvert installation just north of the RXR tracks.

Thursday, August 27, 2026

Sidewalk has been placed in the 1200 block of 3rd Ave.  Storm sewer work has been completed in the Chestnut intersection and will be open for the detour route by 8-28.  Class 5 has been placed in the 1300 and the1400 blocks.  Subgrade preparation is ongoing in the 1500 and 1600 blocks.  The Spruce St. intersection will close on 8-28 for subgrade preparation thus making Chestnut St. the detour route again.  

Upcoming work is curb and gutter installation in the 1300 and 1400 blocks.

Thursday, August 27, 2026

Recent progress – Sewer and water services are currently being installed on 3rdAvenue between Spruce Street and Pine Street.  Storm drain work at 3rdAvenue/Chestnut Street intersection is expected to begin Friday, August 21 and last through Wednesday, August 26th.  Access for residents in the neighborhood to the west of 3rd Avenue will be at the intersection of 3rd Avenue and Spruce Street during that time period.  Sidewalks are currently being installed on the south side of the project.  

Upcoming work expected – Storm Drain installation at 3rdAvenue/Chestnut intersection will continue along with subgrade excavation/preparation and the placement of aggregate base at the intersection.  Sewer and water service work will continue between Spruce Street and Pine Street.  Miscellaneous concrete work will continue on the southerly portion of the project.

Wednesday, August 12, 2026

Storm sewer work is ongoing in the 1700 and 1600 blocks.  Gas main work is ongoing in the 2000 and 1900 blocks.  Sidewalk has been installed in the 1200 block on the west side of 3rd Avenue.  Utility poles are being installed in the 1500 block.  Service work is ongoing in the 1300 to 1600 blocks.  The Chestnut St. crossing is still open.  The Pine St. intersection is closed for storm sewer installation.

Wednesday, August 5, 2026

Gas contractor is in the Pine St. intersection and working north to RR tracks.  Sanitary & water services are being worked on in the 1300-1600 blocks.  Sanitary main line has been completed from the 1300 block north to the RR tracks.  Curb and gutter staking is being preformed from Riverfront to the 1300 block.  Upcoming work is storm sewer installation in the 1300 - 1600 blocks and service work in the same area.

Thursday, July 30, 2026

Gas company is working in Pine St. continuing around the corner to the RR tracks.  Watermain and sanitary main has been installed in the 1700 block.  Crews are working on sanitary main in the 1400 block.  Chestnut St. is open for the detour route at this time.  Upcoming is storm sewer work.

Wednesday, July 22, 2026

Gas company is working in the 2000 block using flaggers to direct one lane traffic.  Storm sewer work is ongoing in the Maxfield intersection.  Sanitary sewer work is ongoing thru the Chestnut intersection.  The detour is going through Spruce St. while pine street is closed for gas main and sewer and water work is ongoing.  The detour will go back to Chestnut St. when the utilities are finished in that area.  Class 5 has been placed in the 1200 block.  Fiber conduit is going in on east side of 3rd Ave. in the 1300 block.  Upcoming work is the railroad crossing is going to be repaired by the railroad company.  

Thursday, July 16, 2026

Gas company is working in the 2000 block with flag people present at all times during work hours.  Sanitary sewer work is ongoing in the Pine Street intersection.  3rd Avenue is closed going south from Brooks Street with the detour on Chestnut Street to 4th Avenue being the way to get to Pine Street.  Service work is going on in the 1400 block.  Road bed preparation is ongoing in the 1200 & 1300 blocks of 3rd Avenue.

Friday, July 10, 2026

The gas company is working in the 2100 block, flaggers on site for traffic control.  Watermain has been installed in the 1200 and 1300 blocks going through the testing process.  Sanitary sewer has been installed in 1200 block.  Temporary water services have been installed at the ROW in the 1300-1600 blocks.  Utility pole work is ongoing in the 1300-1600 blocks.  Trees are being cut along the whole roadway.  Upcoming work is storm sewer, water and sanitary service work in the 1200 block.

Friday, July 10, 2026

Storm sewer work going on in the 1200 block.  Watermain installation is ongoing in the 1400 block.  Watermain testing is taking place in the 1300 block.  Gas main work is happening in the 2100 block.  Upcoming work is service work and storm sewer installation in the 1300 block.

Friday, July 10, 2026

Gas main is working in the 2100 block.  Watermain is being installed in the 1500 block.  Chestnut has been shut down for watermain install.  Pine St. is open for crossing 3rd Ave.  Storm sewer has been installed in the 1200 block along with the service work.  They are removing subgrade in 1200 block.  Ongoing utility pole work in phase 1.  Pine St. will be closed 7-13-2026 and planned for a two week closure.  Access to Germania neighborhood will be at Chestnut St.

Wednesday, June 17, 2026

Sanitary sewer and watermain are being installed in the 1200 block of 3rd Ave.  Roadway removals are taking place week of 6-15.  Gas main has been installed through the Cleveland intersection and traffic on 3rd Ave. has been switched over to two way traffic on the west side of 3rd Ave. utilizing the median as cross over area.

Tuesday, June 16, 2026

Gas company is working on installation of 16" main in 2100 block.  Contractor is removing existing roadway from Riverfront to Maxfield.  They are are also setting up the temporary water system in that same area.

Tuesday, May 19, 2026

Utility installation has begun in the 2100 block of 3rd avenue.