HOME MenuWoodhaven Circle Stormwater Improvements
Storm sewer improvements, grading and roadway patching.
Latest project update
Thursday, September 10, 2026
Traffic control was installed this week along with erosion control. Work will begin the week of 9/14 and is expected to take three weeks. Woodhaven Circle will be fully closed to thru traffic for the duration of the project.