Storm sewer improvements, grading and roadway patching.
Project updates
Thursday, September 10, 2026
Traffic control was installed this week along with erosion control. Work will begin the week of 9/14 and is expected to take three weeks. Woodhaven Circle will be fully closed to thru traffic for the duration of the project. Thursday, September 3, 2026
Woodhaven Circle Stormwater Improvements are scheduled to start on 9/8. Traffic control will go into place the morning of 9/8 closing the road to thru traffic. The project is projected to take three weeks to complete. Thursday, August 27, 2026
Project is expected to start on Tuesday, September 8th. Expect contractor mobilization, traffic control setup, and removals to occur initially. Thursday, August 27, 2026
The preconstruction and neighborhood meetings were held on Wednesday, August 19th. There was a good turnout for the neighborhood meeting where the scope of the project and schedule were outlined and discussed. The project is projected to begin September 8th pending any delays with material delivery or weather. Thursday, August 13, 2026
Preconstruction meeting and Neighborhood meeting is currently getting scheduled. Construction commencement to follow.