Woodhaven Circle Stormwater Improvements Project updates

Print
Press Enter to show all options, press Tab go to next option
Storm sewer improvements, grading and roadway patching.

Project updates

Thursday, November 19, 2026

Work is complete.

Friday, November 13, 2026

Project is complete.  No Activity.

Thursday, November 5, 2026

No activity.  This project is complete.

Friday, October 30, 2026

No activity.  This project is complete.

Thursday, October 22, 2026

Project is complete.  The contractor removed the traffic control signage this week.

Thursday, October 15, 2026

The project is complete.  The traffic control signage will be removed in the coming week.

Thursday, October 8, 2026

The Woodhaven Circle Stormwater Improvement is complete with the sod being placed this week.  We will be conducting a punch list walk to identify any deficiencies that need to be addressed prior to final acceptance of the project.

Thursday, October 1, 2026

The stormwater work is complete and the roadway is restored. There is some minor grading work to complete and then contractor will be laying the sod in the next couple of days. Once the sod is done work will be complete.  

Friday, September 25, 2026

Castings for the catch basins within the curb were set this week, concrete work was completed, and paving was completed.  Turf restoration work remains and will take place the week of 9/28 depending on weather delays.

Thursday, September 17, 2026

The contractor is waiting to receive some materials which need to be installed prior to concrete and asphalt work.  They are expecting to have the materials early the week of 9/21 and planning to do the concrete work later in the week with the paving work to follow.  The drainage swale is complete with the exception of the turf that needs to be placed once the remainder of the site is ready for turf.  

Thursday, September 10, 2026

Traffic control was installed this week along with erosion control.  Work will begin the week of 9/14 and is expected to take three weeks.  Woodhaven Circle will be fully closed to thru traffic for the duration of the project.

Thursday, September 3, 2026

Woodhaven Circle Stormwater Improvements are scheduled to start on 9/8.  Traffic control will go into place the morning of 9/8 closing the road to thru traffic.  The project is projected to take three weeks to complete.

Thursday, August 27, 2026

Project is expected to start on Tuesday, September 8th.  Expect contractor mobilization, traffic control setup, and removals to occur initially.

Thursday, August 27, 2026

The preconstruction and neighborhood meetings were held on Wednesday, August 19th.  There was a good turnout for the neighborhood meeting where the scope of the project and schedule were outlined and discussed.  The project is projected to begin September 8th pending any delays with material delivery or weather. 

Thursday, August 13, 2026

Preconstruction meeting and Neighborhood meeting is currently getting scheduled.  Construction commencement to follow.