HOME MenuGermania Park Phase 4 Project updates
Suggested improvements include complete reconstruction including complete replacement of all pavements, sanitary sewer, sanitary sewer, water main, storm drains were needed, branch services to each lot, concrete curb and gutter and driveways as applicable. These improvements were determined though a review and evaluation of city infrastructure and an extensive public engagement process. This was done to provide context sensitive improvements that mentioned the reliability of service for the neighborhood.
Project updates
Friday, November 13, 2026
No activity on site this week. Project is complete and closed out.Tuesday, November 3, 2026
No activity on site this week.Friday, October 16, 2026
Wear course layer of asphalt was installed on 6th Avenue between Harper Street and Cleveland Street on Friday, October 9th.Friday, October 9, 2026
Wear course bituminous pavement was installed on 6th Avenue between Harper Street and Cleveland Street on Friday, October 9th.Friday, October 2, 2026
No activity on site this week.Friday, September 25, 2026
No activity on site this week.Friday, September 18, 2026
No activity on site this week.Friday, September 11, 2026
No activities on site this week.Friday, September 4, 2026
No activity on site this week.Thursday, August 27, 2026
No activity on site this week.Thursday, August 27, 2026
No activity on site this week.Thursday, August 13, 2026
No activity on site this week.Friday, August 7, 2026
No activity on site this week.Friday, July 31, 2026
No activity on site this week.Friday, July 24, 2026
Final lift of asphalt was placed on the project besides 6th Avenue between Harper Street and Cleveland Street this week. Expect 6th Avenue final lift of asphalt to be placed in a few weeks. Notices of work will be posted a couple of days prior to work starting.Wednesday, July 22, 2026

Final paving is scheduled to start Tuesday, July 21st and will conclude by end of day Wednesday, July 22nd. Final paving for 6th Avenue between Harper Street and Cleveland Street has been delayed and will not be completed during this time period and will be completed late summer or early fall.