Germania Park Phase 4 Project updates

Print
Press Enter to show all options, press Tab go to next option

Suggested improvements include complete reconstruction including complete replacement of all pavements, sanitary sewer, sanitary sewer, water main, storm drains were needed, branch services to each lot, concrete curb and gutter and driveways as applicable. These improvements were determined though a review and evaluation of city infrastructure and an extensive public engagement process.  This was done to provide context sensitive improvements that mentioned the reliability of service for the neighborhood.

Project updates

Friday, September 11, 2026

No activities on site this week.

Friday, September 4, 2026

No activity on site this week.

Thursday, August 27, 2026

No activity on site this week.

Thursday, August 27, 2026

No activity on site this week.

Thursday, August 13, 2026

No activity on site this week.

Friday, August 7, 2026

No activity on site this week.

Friday, July 31, 2026

No activity on site this week.

Friday, July 24, 2026

Final lift of asphalt was placed on the project besides 6th Avenue between Harper Street and Cleveland Street this week.  Expect 6th Avenue final lift of asphalt to be placed in a few weeks.  Notices of work will be posted a couple of days prior to work starting.

Wednesday, July 22, 2026

Final paving is scheduled to start Tuesday, July 21st and will conclude by end of day Wednesday, July 22nd.  Final paving for 6th Avenue between Harper Street and Cleveland Street has been delayed and will not be completed during this time period and will be completed late summer or early fall.

Friday, July 10, 2026

Drainage repairs throughout the project have been completed as of Friday, July 10th.  Expect final punch list work to be performed in the coming weeks.  Final paving will occur after punch list items are addressed; this will be several weeks out and we will notify adjacent residents by door hanger.

Wednesday, September 17, 2025

Contractor to check every water service and lower depths if needed. Work on services will start Sept.19, with driveway asphalt ramping to follow after.

Thursday, May 22, 2025

6th Ave and asphalt driveways have been paved. Contractor is working on concrete driveways.

Thursday, May 1, 2025

Water and sewer on 6th ave are installed. All services are completed. The contractor will start grading on 6th ave.

Monday, April 28, 2025

Installing sewer and water main from Harper Street to Cleveland.

Monday, April 28, 2025

4th ave, 5th ave, and Lind st are completed. Starting construction on 6th ave in the spring.

Thursday, October 24, 2024

Sixth Ave. has been pushed to spring. Water and sewer mains are complete, just waiting for testing to be completed. Starting on Fifth Ave. services on 10/10/24. Grading on Fourth Ave. has started and will continue to Lind St..

Thursday, October 24, 2024

Services are installed. Gradings on 5th ave and Lind st are started and will continue into next week 10/28.

Wednesday, September 25, 2024

Water and sewer mains are placed on 5th Avenue from Harper Street to Columbia park. Currently working on adding services to 4th Avenue, contractor plans to be finished with 4th Avenue services this week 9/27/24.

Thursday, September 19, 2024

Sewer and water on Fourth ave are complete, it still needs backfilling. Contactor is continuing to excavate rock and place water on Lind st between Fourth and Fifth ave.

Thursday, September 5, 2024

Asphalt is being removed on Fifth Avenue and rock excavation on Fourth Avenue is continuing.

Wednesday, August 14, 2024

Asphalt removed on 4th Avenue and Lind Street from 3rd Avenue to 5th Avenue. Rock excavation started on 4th Avenue.

Tuesday, July 30, 2024

Tree removal to take place this week.