Lowering the primary weir elevation, expanding outlet capacity, and replacing the existing emergency overflow.
Project updates
Thursday, November 19, 2026
Final lift of bituminous is complete. Rip rap has been installed on the pond side of overflow pipe. Sod has been installed on 11-18 and the road signs have been pulled making the road open traffic.
Upcoming work includes sod care.
Tuesday, November 10, 2026
Pipe work is complete. Curb and gutter and the sidewalk are complete. Black dirt has been placed on west side of street. Survey stakes have been set for the blacktop working pad on east side of road. Gravel base being set up for pavement.
Upcoming work will include fine grading of road section, and parking pad. Slope restoration on the east side. Bituminous pavement of road section and parking pad. Sod installation.
Tuesday, November 3, 2026
The arch pipe has been installed through the road section. The watermain has been adjusted to provide clearance for the arch pipe. Rip rap has been placed on the west end of the outlet pipe. Aggregate has been placed on road section to stabilize the road during the this week's rain event which has slowed progress of the pipe installation. Final three pipe sections have been delivered and will be installed with apron as soon as the weather permits.
Upcoming work includes finishing the pipe install. Class 5 gravel in the road section followed by curb and gutter and bituminous pavement.
Thursday, October 29, 2026
Half of the arch pipe has been installed. The watermain was moved out of the way of the new pipe. Upcoming work includes finishing the arch pipe overflow install. Rip rap the outlet end of pipe. Prepare the road for curb and gutter and paving. Thursday, October 22, 2026
The new arch storm pipe is being delivered. Stakes have been placed for apron ends. The weir has been modified, and the new top of structure has been placed. Upcoming work includes watermain adjustment. Installation of the new arch pipe overflow. Wednesday, October 14, 2026
Storm structure has arrived on site along with the pipe aprons. Upcoming work will be a gravel crossing installed across the work zone for the Mankato marathon race on 10-17. Pipe delivery and install the week of 10-19. Thursday, October 8, 2026
Road signage has been deployed. The silt fence has been installed, and removals are in process. Upcoming work includes the delivery of the reinforced concrete pipe and excavation for the pipe install. Friday, October 2, 2026
Contractor is currently mobilizing onto the site. Expect South Brook Circle to close on Friday, October 2nd between 209 and 213 South Brook Circle for the one month duration of the project. Thursday, October 1, 2026
Work will begin on overflow pipe project on 10-2-2026. Southbrook Circle will be closed at the work area by the pond outlet to the creek. Upcoming work will be removal of the roadway and the existing overflow pipe. Estimated project duration is one month depending on weather. Friday, September 25, 2026
No activity on site this week. Friday, September 18, 2026
Neighborhood meeting for project held on the evening of Tuesday, September 15th. Project is scheduled to begin in early October and is expected to last one month weather permitting. Friday, September 11, 2026
No activity on site this week.