Highlighted sections on the map show street construction areas.

X

2025 Adams Street Resurfacing (Alleys and Misc. Sidewalks)

Project Type: Construction Projects

Pavement rehabilitation of Adams Street from Hwy 22 to Raintree Road, Alley 6-331B (Harper St. and 7th Ave.), Alley 7-208 (Maxfield and 3rd Ave.), Alleys 18-301 and 18-302 (Byron St.to Parsons St.).

  • Project Manager: Lucas Pederson
  • Project Valuation: $922,551
  • RSS Feed

2026 Resurfacing (Main Street, Dolph Road and Miscellaneous Sidewalks)

Project Type: Construction Projects

East Main Street, Dolph Reservoir Access Road and Miscellaneous Sidewalks

  • Project Manager: Lucas Pederson
  • Project Valuation: $2,553,612
  • Project Contractor: W W Blacktopping, Inc.
  • RSS Feed

3rd Avenue (CSAH 5)

Project Type: Construction Projects

Reconstruction of 3rd Avenue (CSAH 5) from Riverfront Drive to Cleveland Street.

  • Project Manager: Lucas Pederson
  • Project Valuation: $9,157,660
  • Project Contractor: Holtmeier Construction, Inc.
  • RSS Feed

Bassett Drive Extension

Project Type: Construction Projects

Bassett Drive Extension from the centerline of Carver Road to approximately 1300' to the east.

  • Project Manager: Lucas Pederson
  • Project Valuation: $1,101,491
  • Project Contractor: Dirt Merchant, Inc.
  • RSS Feed

Belleview Avenue, Jayro Court, and Riverview Street Improvement Project

Project Type: Construction Projects

Reconstruction of Belleview Avenue from Woodshire Drive to Swiss Street - Jayro Court from Belleview Avenue to its northern terminus - Riverview Street from Belleview Avenue to its northern terminus

  • Project Manager: Lucas Pederson
  • Project Valuation: $1,497,964
  • Project Contractor: W W Blacktopping, Inc.
  • RSS Feed

Germania Park Phase 4

Project Type: Construction Projects

Reconstruction of Lind St from 3rd Ave to 6th Ave, 4th Ave from Harper St to Lind St, 5th Ave from Harper St to Cleveland St, 6th Ave from Harper St to Cleveland St.

  • Project Manager: Lucas Pederson
  • Project Valuation: $2,433,767
  • RSS Feed

Germania Park Phase 5

Project Type: Construction Projects

Reconstruction of 7th Avenue from Harper Street to Cleveland Street, 8th Avenue from Harper Street to Cleveland Street, Lind Street from 6th Avenue to the eastern terminus and Cleveland Street from 7th Avenue to the eastern terminus.

  • Project Manager: Lucas Pederson
  • Project Valuation: $1,440,614
  • RSS Feed

Hiniker Parkway, Hiniker Pond Park Parking Lot, and Range Street

Project Type: Construction Projects

Construction of Hiniker Parkway from Butterworth Street to W Lind Street and Hiniker Pond Park Parking Lot

  • Project Manager: Lucas Pederson
  • Project Valuation: $1,742,072
  • Project Contractor: Dirt Merchant, Inc.
  • RSS Feed

Kern Bridge

Project Type: Construction Projects

Improvements include rehabilitating/re-erecting the Historic Kern Bridge, approach spans, trail construction, lighting and signage.

  • Project Manager: Lucas Pederson
  • Project Valuation: $10,516,004
  • Project Contractor: Redstone Construction, LLC
  • RSS Feed

Land of Memories Trail

Project Type: Construction Projects

A trail proposed to be constructed through Land of Memories Park connecting the eastern terminus of Amos Owen lane with the Minneopa Trail.

  • Project Manager: Lucas Pederson
  • Project Valuation: $577,482
  • Project Contractor: Nielsen Blacktopping, Inc.
  • RSS Feed

Rosewood Pond Outlet Improvements

Project Type: Construction Projects

Improvements to the existing Rosewood Pond outlet infrastructure on South Brook Circle between Alexander Court and South Brook Way.

  • Project Manager: Lucas Pederson
  • Project Valuation: $328,185
  • Project Contractor: Broemeling Excavating, Inc.
  • RSS Feed

Veterans Memorial Bridge and Hwy 169/Belgrade Interchange

Project Type: Construction Projects

Planned bridge and ramp improvements at Hwy 169 and Belgrade Ave. in North Mankato and Mankato include repairs to Veterans Memorial Bridge, new interchange signals, improved ramp pavement, and replaced sidewalks.

  • Project Manager: Lucas Pederson
  • Project Valuation: $21,300,000
  • RSS Feed

Woodhaven Circle Stormwater Improvements

Project Type: Construction Projects

Storm sewer improvements.

  • Project Manager: Lucas Pederson
  • Project Valuation: $85,000
  • Project Contractor: Dirt Merchant, Inc.